Discover which plan provides the Business Case with costs during PRINCE2’s Initiating a Project process. Learn how this plan helps establish a solid foundation for your project’s success.
Question
Which plan provides the Business Case with costs during the Initiating a Project process?
A. Initiation Stage Plan
B. Project Plan
C. Stage Plan
D. Team Plan
Answer
A. Initiation Stage Plan
Explanation
The Initiation Stage Plan is the correct answer. This plan, created during the Initiating a Project process, outlines the activities, resources, and costs required to complete the initiation stage. It provides the Business Case with the necessary cost information to assess the project’s viability and make informed decisions. The Initiation Stage Plan is a crucial component in establishing a solid foundation for the project and ensuring that all stakeholders have a clear understanding of the project’s objectives, scope, and costs.
PRINCE2 Foundation certification exam practice question and answer (Q&A) dump with detail explanation and reference available free, helpful to pass the PRINCE2 Foundation exam and earn PRINCE2 Foundation certification.
The post PRINCE2 Foundation: Uncover the Plan Behind Project Costs in PRINCE2’s Initiating a Project Process appeared first on PUPUWEB - Tech Solution and Advice from Pro.
This post first appeared on PUPUWEB - Information Resource For Emerging Technology Trends And Cybersecurity, please read the originial post: here