PRINCE2 Foundation: Uncover the Plan Behind Project Costs in PRINCE2’s Initiating a Project Process

Discover which plan provides the Business Case with costs during PRINCE2’s Initiating a Project process. Learn how this plan helps establish a solid foundation for your project’s success.

Question

Which plan provides the Business Case with costs during the Initiating a Project process?

A. Initiation Stage Plan
B. Project Plan
C. Stage Plan
D. Team Plan

Answer

A. Initiation Stage Plan

Explanation

The Initiation Stage Plan is the correct answer. This plan, created during the Initiating a Project process, outlines the activities, resources, and costs required to complete the initiation stage. It provides the Business Case with the necessary cost information to assess the project’s viability and make informed decisions. The Initiation Stage Plan is a crucial component in establishing a solid foundation for the project and ensuring that all stakeholders have a clear understanding of the project’s objectives, scope, and costs.

PRINCE2 Foundation certification exam practice question and answer (Q&A) dump with detail explanation and reference available free, helpful to pass the PRINCE2 Foundation exam and earn PRINCE2 Foundation certification.

The post PRINCE2 Foundation: Uncover the Plan Behind Project Costs in PRINCE2’s Initiating a Project Process appeared first on PUPUWEB - Tech Solution and Advice from Pro.



This post first appeared on PUPUWEB - Information Resource For Emerging Technology Trends And Cybersecurity, please read the originial post: here

Share the post

PRINCE2 Foundation: Uncover the Plan Behind Project Costs in PRINCE2’s Initiating a Project Process

×

Subscribe to Pupuweb - Information Resource For Emerging Technology Trends And Cybersecurity

Get updates delivered right to your inbox!

Thank you for your subscription

×