Sparks flew at a New Orleans City Council’s utility committee meeting on Valentine’s Day, compelling the committee to delay voting on a resolution that would scrap plans to rescind the permit for Entergy’s proposed $210 million natural gas power plant in exchange for a $5 million fine.
The contentious permit was awarded to Entergy, which provides power to the city, on March 18, 2018, but the city council's third-party investigation of Entergy found the allegations that the company took part in an Astroturf Campaign to influence the vote for its proposed New Orleans East gas plant to be true. The investigation concluded that the company was responsible for hiring paid actors, who were wearing t-shirts supporting the plant, to fill council chambers and speak in support of the project.
This post first appeared on DeSmogBlog | Clearing The PR Pollution That Clouds, please read the originial post: here