Estimating the cost of excavation on earthwork projects can be a complex process. There are many factors to consider, including the type of Soil, the depth of excavation, the distance from the excavation site to the disposal area, and the type of equipment needed. In this article, we will provide tips on how to accurately estimate the cost of excavation on earthwork projects.


Determine the scope of the project: The first step in estimating the cost of excavation is to determine the scope of the project. This includes the size and depth of the excavation, as well as the type of soil that needs to be removed.


Assess the soil conditions: The type of soil can have a significant impact on the cost of excavation. For example, clay soil is more difficult to excavate than sand, and will therefore cost more. It is important to assess the soil conditions before starting the project to get a better understanding of the challenges and costs involved.


Consider the equipment needed: Different types of excavation projects will require different types of equipment. For example, a small excavation project may only require a backhoe, while a larger project may require a bulldozer or an excavator. The cost of the equipment will need to be factored into the overall cost of the project.


Determine the disposal costs: The cost of disposal is another important factor to consider when estimating the cost of excavation. This includes the cost of transporting the soil to a disposal site, as well as any fees associated with disposing of the soil.


Get quotes from multiple contractors: To get the most accurate estimate, it is a good idea to get quotes from multiple contractors. This will allow you to compare prices and choose the best option for your project.


In conclusion, accurately estimating the cost of excavation on earthwork projects requires careful consideration of the scope of the project, the soil conditions, the equipment needed, and the disposal costs. By following these tips, you can ensure that your project stays within budget and is completed on time.






To calculate the Earth Work in Excavation, we have to find the volume of the excavation.

To calculate the volume we have to take Length, Breadth and Depth of the foundation, and add 100mm (may be more, as per site requirements) extra in length and breadth for shuttering works.

Suppose, the length of the foundation is 3400mm

Breadth of the foundation is 2600mm, and the depth is 5400mm and the soling is 75mm and pcc over the soling in 75mm and number of foundation is 15, then our values will be

L = 3400+100=3500 or 3.5m

B = 2600+100=2700 or 2.7m

D = 5400+150= 5550 or 5.55m

And our calculation for excavation in earth work will be (Length X Breadth X Depth)

=3.5 x 2.7 x 5.55 mᶟ

=52.45 mᶟ

For 15nos. of foundation , 15 x 52.45 cu m = 786.75 mᶟ

Great Republic Day Sale on Business purchases

Sl. No

Description of Item

Nos.

Length

Breadth

Depth

Quantity

Unit

1

Excavation in Earth Work

15

3.5

2.7

5.55

786.75

Cu m

Great Republic Day Sale on Business purchases


This post first appeared on I Am A Civil Engineer, please read the originial post: here

Share the post

Estimate for Earth Work in Excavation

×

Subscribe to I Am A Civil Engineer

Get updates delivered right to your inbox!

Thank you for your subscription

×