Microsoft Project on Steroids II | Project Management Portmanteau Blog | 2022

Posted at 21:16h in Project Management Training by admin 0 Comments
4. CV (EVM) is EV (EVM) – AC (EVM) (You can use CV if you used BCWP in point 3). For summary tasks, we use the formula (but you could do a rollup-sum):
5. SV (EVM) is EV (EVM) – PV (EVM) (You can use SV if you used BCWP in point 3). For summary tasks, we use the formula (but you could do a rollup-sum):
6. CPI (EVM):
The thresholds used here are only an example. These values can be changed to reflect what you consider good, average, warning, and bad values.
7. SPI (EVM):
The thresholds used here are only an example. These values could be changed to reflect what you consider good, average, warning, and bad values.
J



This post first appeared on Project Management Portmanteau, please read the originial post: here

Share the post

Microsoft Project on Steroids II | Project Management Portmanteau Blog | 2022

×

Subscribe to Project Management Portmanteau

Get updates delivered right to your inbox!

Thank you for your subscription

×