Navigator cancels proposed Midwestern CO2 pipeline, citing ‘unpredictable’ regulatory processes | Federal News Network

BISMARCK, N.D. (AP) — A company on Friday said it would cancel its plans for a 1,300-mile (2,092-kilometer) Pipeline across five Midwestern states that would have gathered carbon dioxide emissions from ethanol plants and buried the gas deep underground.

Navigator CO2 Ventures’ Heartland Greenway project is among a handful of similar ventures supported by the renewable fuels industry and farming organizations, but many landowners and environmental groups oppose the pipelines and question their safety and effectiveness in reducing climate-warming gases.

In a written statement, the company said the “unpredictable nature of the regulatory and government processes involved, particularly in South Dakota and Iowa” were key to the decision to cancel the project.

Navigator’s pipeline would have carried planet-warming CO2 emissions from more than 20 plants across Illinois, Iowa, Minnesota, Nebraska and South Dakota for permanent storage deep underground in Illinois.

Iowa Renewable Fuels Association Executive Director Monte Shaw said carbon capture projects are “the best way to align ethanol production with the increasing demand for low carbon fuels both at home and abroad,” and are essential “to unlocking the 100-billion-gallon sustainable aviation fuel market for agriculture, in the long term.”

“It is not an overstatement to say that decisions made over the next few months will likely place agriculture on one of two paths. One would lead to 1990s stagnation as corn production exceeds demand, and the other opens new market opportunities larger than anything we’ve ever seen before,” he said in a statement.

Navigator earlier this month withdrew its application for a crucial permit in Illinois, and also said it was putting all of its permit applications on hold. Those moves came after South Dakota public utilities regulators denied Navigator a construction permit in September.

The pipeline would have used carbon capture technology, which supporters tout as a combatant of climate change, with federal tax incentives and billions of dollars from Congress, making such efforts lucrative. But opponents question the technology at scale, and say it could require bigger investments than less expensive alternatives such as solar and wind power.

CO2 pipelines have faced pushback from landowners, who fear a pipeline rupture and that their land will be taken from them for the projects.

Pipeline opponents welcomed Navigator’s announcement Friday.

“Everyone said we have no chance against foreign-backed, multibillion-dollar hazardous pipelines but when hundreds of landowners band together with a unified legal strategy, we can win,” said Brian Jorde, an Omaha-based attorney who represents many landowners opposed to Midwestern pipeline projects.

Regulatory panels in North Dakota and South Dakota dealt blows to Summit Carbon Solutions’ proposed $5.5 billion, 2,000-mile (3,219-kilometer) interstate pipeline network. The system would carry CO2 emissions from more than 30 ethanol plants in Iowa, Minnesota, Nebraska, North Dakota and South Dakota, to be buried deep underground in central North Dakota.

North Dakota regulators denied Summit a siting permit, but granted the company’s request for reconsideration. The South Dakota panel denied the company’s permit application, but Summit intends to reapply.

Iowa regulators this month suspended a weekslong hearing for Summit’s project, set to resume next month. Minnesota regulators are proceeding with an environmental review for a small part of Summit’s project.

Copyright
© 2023 The Associated Press. All rights reserved. This website is not intended for users located within the European Economic Area.

The post Navigator cancels proposed Midwestern CO2 pipeline, citing ‘unpredictable’ regulatory processes | Federal News Network appeared first on Al Jazeera News Today.



This post first appeared on Al Jazeera News Today, please read the originial post: here

Share the post

Navigator cancels proposed Midwestern CO2 pipeline, citing ‘unpredictable’ regulatory processes | Federal News Network

×

Subscribe to Al Jazeera News Today

Get updates delivered right to your inbox!

Thank you for your subscription

×