In its September 18, 2017 decision, the GAO sustained a protest over a task order awarded to a contractor whom only had one of the two required services listed on their General Services Administration (“GSA”) Federal Supply Schedule (“FSS”).

The United States Navy attempted to acquire 120-250 hotel rooms for civil service mariners in the Norfolk, Virginia area. The Agency invited vendors to submit offers through the GSA’s e-buy system, with instructions to only submit services on a current GSA Schedule contract. Unfortunately for the awardee, the request for quotation (“RFQ”) also required shuttles from the hotels to the work sites.

While the decision takes pains to describe in detail the intricacies of GSA Schedules, the result is simple. The original awardee simply did not have transportation services included as “additional services” as required. The RFQ listed two separate tasks orders, one of which was transportation by shuttle. Despite the awardee’s ability to provide these services, the RFQ clearly emphasized the award would be made exclusively through the GSA thereby excluding companies without all required services listed on the Schedule.

About the Author:

Tyler Freiberger
Associate Attorney

Tyler Freiberger is an associate attorney at Centre Law & Consulting primarily focusing on employment law and litigation. He has successfully litigated employment issues before the EEOC, MSPB, local counties human rights commissions, the United States D.C. District Court, Maryland District Court, and the Eastern District of Virginia.



This post first appeared on Centre Knowledge, please read the originial post: here

Share the post

GSA Federal Supply Schedule Description Too Limited For Contractor to Receive Award

×

Subscribe to Centre Knowledge

Get updates delivered right to your inbox!

Thank you for your subscription

×