Production TestsUnless otherwise specified, all Production Tests shall be made by the manufacturer at the factory on the complete MEI switchgear or its component for the purpose of checking the correctness of manufacturing operations and materials. (See ANSI/IEEE C37.20.3-1987.) Production tests shall include the following:1) Low-frequency withstand voltage tests 2) Mechanical operation tests 3)