Get Even More Visitors To Your Blog, Upgrade To A Business Listing >>

Woodeen Homes 2010

1.Spesification for wooden homes

A. Tipes of wood:
-ironwood frame
-ironwood floor
-ironwood walls
-ironwood trusses and rafters
-dipterocarp ceiling.

B. Lumber sizes
-pilars 20cmx20cm first floor ( grounds floor)
-pilars 10cmx10cm seconds floor
-flooring 3cmx17cm
-primary runnersor floor joists 10cmx20cm
-secondary runners or floor joists 6cmx16cm
-tongue-and-groove walling 2cmx9cm
-primary roof runners 5cmx10cm
-secondary roof runners 6cmx6cmtongue-and groove ceilling 1cmx8cm
-door frame 10cmx10cm, 5cmx10cm
-door standart
-windows frame 10cmx10cm
-windows standart

C.Roofing material / Accessorries
-tile
-composite
-paneling
-ralling
-orramental bannister and railling supports
-glass
-hinges
door knobs and handles
-and miscellaneous items

D.Estimated time reguired for pre-fabrycation depends upon the model chosen as follows:
-models 72 m2 - 5 weeks / 30 work days
-models 144 m2 - 7 weeks / 42 work days
-models 160 m2 - 8 weeks / 50 work days
-models 200 m2 - 12 weeks / 75 work days
on-site assembly

2.Cost and method of payment
a. Price in indonesia rupiah 2.250.000/ m2( square meter)
cost of pre-fabrication within Indonesia
b. Down payments : 50% of total pre-fabrication cost we will start pre-fabrication as soon as
we receive the down payment.
c. Second payment : 30% of total pre-fabrication cost when the materials and workers arrive
at the assembly site.
d. third ( last) payment : 20% of total pre-fabrication cost uponcompletion of assembly.



This post first appeared on Interior Home I Architecture I Home Design, please read the originial post: here

Share the post

Woodeen Homes 2010

×

Subscribe to Interior Home I Architecture I Home Design

Get updates delivered right to your inbox!

Thank you for your subscription

×